BRISBANE, AUSTRALIA: Kangaroo Point Green Bridge has reached a new construction milestone with the final piece of the 95-metre-tall mast centrepiece installed by Marr Contracting’s M2480D tower crane working on the project.

Located on Brisbane’s busy river, the key challenge for the project was how to construct the bridge mast the while minimising potential impacts on the public ferries and private vessels that use the Brisbane River daily.

The BESIX Watpac-led consortium, Connect Brisbane, who is delivering the project on behalf of Brisbane City Council, engaged Marr early in the design phase to develop a lifting strategy that supported their preferred construction methodology and addressed the challenges of constructing the 95-metre-tall mast.

According to BESIX Watpac Project Director, Rowan Riggall, “Our in-house engineering team was instrumental in identifying this crane at tender phase as the preferred lifting solution for the project. After comparing barge crane and tower crane options, the team confirmed the M2480D was the most suitable crane in the Australian market capable of lifting the fully assembled mast head.”

Working with Marr’s Brisbane-based engineers, Robert Bird Group, Marr developed a solution using an M2480D Heavy Lift Luffing (HLL) tower crane with a 64-metre-long boom installed on a platform in the middle of Brisbane River.

This configuration allowed the 25-metre-tall pre-fabricated steel masthead weighing 180 tonnes to be lifted to a height of 95 metres ­– a feat that wouldn’t have been possible using a more traditional approach of crawler cranes.

The lift was the heaviest to be undertaken as part of Marr’s scope of work including more than 10 major lifts and general construction lifting requirements over a period of 12 months.

“Reaping the benefits of modularised construction with fewer, heavier lifts is not only helping to deliver a safer, more productive site; but also allowing our client to share the economic benefit delivered by the project by engaging more South East Queensland businesses away from the workfront,” said Marr’s Managing Director, Simon Marr.

 

ABOUT KANGAROO POINT GREEN BRIDGE

An initiative by Brisbane City Council, the Kangaroo Point Green Bridge will be an iconic landmark destination connecting Brisbane’s CBD and eastern suburbs.

At a length of 460 metres, the bridge will be among the longest span cable stay pedestrian and cycle bridges in the world and a must-visit destination in Brisbane.

In June 2021, Brisbane City Council awarded the contract to design and construct the Bridge to the Connect Brisbane, following a detailed procurement process.

Led by BESIX Watpac, the Connect Brisbane consortium consists of bridge design, engineering and construction specialists including Rizzani de Eccher, WSP, Dissing + Weitling, Blight Rayner, Aspect Studios, Right Angle Studios and Rowland.

Construction of the Kangaroo Point Green Bridge is anticipated to be completed in 2024.
Images available for download at: https://www.marr.com.au/media-gallery/kangaroo-point-green-bridge/
Download video: https://vimeo.com/889770224


For more information:

Simon White
Liz Male Consulting
e: simonw@lizmale.co.uk
t: +44 (0)7935 703293

Marr Contracting are world leaders in the design and delivery of heavy lift luffing tower cranes and heavy lifting services. With almost 100 years’ experience working on large-scale construction projects in Australia and around the world, their expertise spans the large-scale construction, mining, oil and gas, power, nuclear, major transport infrastructure, technology and marine sectors. Not just a crew and cranes for hire, they’re big thinkers and problem solvers who love a challenge with a string of ‘world firsts’ to their name – including the world’s largest capacity tower crane, the Marr 2480D Heavy Lift Luffing (HLL) crane. www.marr.com.au

 

SHARE

Related articles

LET'S TALK ABOUT HOW WE COULD ADD VALUE TO YOUR PROJECT

We work with our clients to find a craneage solution that works – no matter how big or complex the job is. And if the right crane doesn’t already exist, we’ll build one to suit the needs of your project.

ABOUT US

We’re not just a crew and cranes for hire. We’re big thinkers and problem solvers who love a challenge. No problem is too big for us.

OUR PHILOSOPHY

We believe that the crane needs to suit the job, not the other way around. We don’t just hire cranes – we design craneage solutions.

OUR HERITAGE

We’re a third-generation family-owned and run business with a strong sense of tradition and loyalty engrained in what we do and how we work together.

OUR PEOPLE

We think of our team as ‘one big family’ of problem-solvers who love cranes and the challenge of working on complex, large-scale projects.

OUR APPROACH

We work with you to find an engineering solution that works. Delivering value through the unique combination of our knowledge, experience, proven service delivery and people.

OUR SERVICES

We’ve worked on some of the most complex and challenging large-scale construction projects across Australia and around the world.

OUR CRANES

We don’t just hire cranes – we design them. So, if the right crane for your job doesn’t already exist, we’ll build one.

OUR PROJECTS

With almost 100 years’ experience, we have a reputation for taking on projects that others can’t or won’t.

SAFETY, QUALITY & ENVIRONMENT

We take on the jobs that many others can’t or won’t – but we always put good business practices first.

SUSTAINABILITY

We take sustainability seriously. It’s inherent in our commitment to finding the best and most efficient solution to every job.

SOCIAL IMPACT

As problem-solvers who love a challenge, we are never shy of tackling the big issues.

DIVERSITY

We are committed to creating a diverse, inclusive and flexible workplace that reflects the clients and communities we work with.