ICD BROOKFIELD PLACE DUBAI

ICD BROOKFIELD PLACE DUBAI

Introducing the world’s largest capacity tower crane to the UAE

SHARE

PROJECT OVERVIEW

When the Multiplex and Ssangyong (MSS) joint venture partners were awarded the main contract to construct ICD Brookfield Place (ICDBP) in Dubai, they turned to Marr Contracting for a heavy lifting solution that would become a first for the world’s ‘crane capital’.

Designed by internationally renowned architects, Foster + Partners, the 282-metre, 54-storey skyscraper’s unique design was challenging from a construction point-of-view. But with a history of working together on iconic projects in Australia for more than 30 years, Multiplex and Marr knew that the best solution required a different way of thinking about craneage for the UAE’s construction sector.

Client
Multiplex and Ssangyong (MSS) Joint Venture
Project
ICD Brookfield Place
Location
Dubai, United Arab Emirates
Sector
HIGH RISE
Date
2017-2019
Cranes

1 x M2480D, 1 x M860DX

THE CHALLENGE

Located in the heart of Dubai’s financial district, the project came with significant challenges including:

  • A complex architectural design featuring complicated steel elements;
  • The need for a cranage solution that could support MSS’ construction methodology, which was based around heavy steel elements;
  • A congested, landlocked site with restricted access and limited space; and
  • An ambitious construction program.
OUR SOLUTION

Multiplex engaged us early in the project and numerous iterations of crane models and sizes were considered during the extensive project planning stage. The original scheme proposed using four smaller M1280D cranes in four locations which would be relocated around the site to lift the structural elements in smaller pieces and weld in-situ.

After meeting with the construction team from Multiplex and their contracted structural steel fabrication supplier, Eversendai, Marr presented an alternative methodology using only two cranes that would be a first for Dubai’s construction sector.

Marr’s solution – using a bespoke 96-tonne capacity M860DX and 330-tonne capacity M2480D heavy lift luffer (HLL) – provided an integrated solution that took into account the heavy lifting requirements from the ground up to the highest point of the building 290-metres above street level.

THE RESULT

ICD Brookfield Place was completed ahead of schedule. Marr’s solution using fewer, larger capacity tower cranes delivered benefits to the project including:

  • Improved safety – fewer lifts, without the need for detailed welding in-situ;
  • Quality – detailed welding carried out in a controlled factory environment offered weld quality assurance;
  • Reduced complexity – less cranes and lower lifting count, and a crane solution aligned to the construction methodology;
  • Time – with the M2480D being set up in only two locations, the time required to set up and shift numerous smaller cranes was eliminated. Use of Marr’s three-beam climbing system also allowed the climb cycle to be completed within 2-3 hours instead of 2-3 days using the traditional method of internal climbing;
  • Productivity – operable in wind speeds of 20m/ second in high winds, our cranes delivered a 99.99% availability rating across the life of the project; and
  • Cost – no requirement for expensive temporary works.
“The success of this project dispels the myth that lots of cranes on a project is a good thing. The best solution is always the safest and most efficient option – and in this case it was the one that used less cranes to drive productivity with fewer, heavy lifts,”

Simon Marr, Managing Director, Marr Contracting

Construction of the building’s distinctive five-storey-high entrance atrium – consisting of five complex steel A-frame nodes weighing up to 85 tonnes – was critical to the construction program.

As the landlocked nature of the site meant that there was no space to employ crawler cranes for the installation of the A-frames nodes, the other ‘traditional’ approach would have been to build the structures in smaller pieces using locally available tower cranes. However, onsite fabrication of the nodes would have created increased safety risks, additional scope and temporary works that would have severely impacted the program. This meant that the ability to lift large, heavy steel components was critical to the construction schedule.

The M2480D was used to drive construction at the lower levels and install heavy structural steel elements from two locations outside the building’s footprint. This allowed each part of the A-Frame to be welded in a controlled factory environment, delivered to the construction zone and lifted directly into place in a single lift.

The M2480D was configured to 110-tonne capacity on a single line, with a 55-metre boom radius and 76-metre free stand height – allowing it to lift large sections of the building’s A-Frame weighing up to 86T in a single lift.

In another first for Dubai’s construction sector, Marr mobilised its unique three-beam climbing system which allowed the M860DX to be placed in the building’s high-rise lift core. The M860DX supported the installation, relocation and removal of the M2480D and assisted the installation of steel sections at the top of the building. It also served as the high-speed heavy lift crane for the construction of the entire building, especially after the M2480D had been removed.

“[The crane] has de-risked the project a lot. For example, implementing an element [such as the nodes] piece-by-piece would involve a lot of temporary works. The manufacturing of these nodes could have taken weeks or months […] if we had to do that on site, so the time benefit is [significant].”

Site visit: ICD Brookfield Place, Downtown Dubai

As the first time a heavy lift luffing tower crane of the M2480D’s size had been used on a high-rise construction project in the UAE, the project was also a game changer for the future of similar projects in the region. On completing this project, the M2480D was engaged by Alec on the construction of Dubai’s One Za’abeel.

LET'S TALK ABOUT HOW WE COULD ADD VALUE TO YOUR PROJECT

We work with our clients to find a craneage solution that works – no matter how big or complex the job is. If the right crane doesn’t already exist, we’ll build one to suit the needs of your project.

ABOUT US

We’re not just a crew and cranes for hire. We’re big thinkers and problem solvers who love a challenge. No problem is too big for us.

OUR PHILOSOPHY

We believe that the crane needs to suit the job, not the other way around. We don’t just hire cranes – we design craneage solutions.

OUR HERITAGE

We’re a third-generation family-owned and run business with a strong sense of tradition and loyalty engrained in what we do and how we work together.

OUR PEOPLE

We think of our team as ‘one big family’ of problem-solvers who love cranes and the challenge of working on complex, large-scale projects.

OUR APPROACH

We work with you to find an engineering solution that works. Delivering value through the unique combination of our knowledge, experience, proven service delivery and people.

OUR SERVICES

We’ve worked on some of the most complex and challenging large-scale construction projects across Australia and around the world.

OUR CRANES

We don’t just hire cranes – we design them. So, if the right crane for your job doesn’t already exist, we’ll build one.

OUR PROJECTS

With almost 100 years’ experience, we have a reputation for taking on projects that others can’t or won’t.

SAFETY, QUALITY & ENVIRONMENT

We take on the jobs that many others can’t or won’t – but we always put good business practices first.

SUSTAINABILITY

We take sustainability seriously. It’s inherent in our commitment to finding the best and most efficient solution to every job.

SOCIAL IMPACT

As problem-solvers who love a challenge, we are never shy of tackling the big issues.

DIVERSITY

We are committed to creating a diverse, inclusive and flexible workplace that reflects the clients and communities we work with.