SYDNEY METRO CROWS NEST STATION

SYDNEY METRO CROWS NEST STATION

A NEW MODEL OF ENGAGEMENT FOR A CHALLENGING CONSTRUCTION SITE

SHARE

PROJECT OVERVIEW

In October 2020, A W Edwards was awarded the contract to construct the new Sydney Metro Crows Nest Station. The AU$370 project included the construction and fit out of the station, including two station entrances, underground platforms, retail space, public domain works and enabling works for future over-station developments.

Eighteen months earlier, Marr’s engineering team were approached by the end-client, Sydney Metro, during the front-end design phase to develop a craneage methodology for the project. Leveraging Marr’s experience in successfully delivering on a number of other Sydney Metro station projects where similar approaches to cut-and-cover method of station box construction had been employed, the goal was to align the craneage solution to Sydney Metro’s preferred precast and modular construction methodology.

As a result, Sydney Metro issued a considered and evaluated design for the construction tenderers with a suitable craneage solution built into it. Marr was subsequently awarded the heavy lifting contract by A W Edwards.

MARR_AW Edwards_Sydney Metro Crows Nest Station
Client
A W EDWARDS
Project
SYDNEY METRO CROWS NEST STATION
Location
SYDNEY, AUSTRALIA
Sector
METRO PROJECTS, MAJOR INFRASTRUCTURE
Date
2018-2024
Cranes
THE CHALLENGE

Following a competitive tender process, construction of the new Crows Nest Station came with a number of challenges including:

  • A constrained site – limited space within the station box construction site to position the cranes;
  • Location – adjacent to one of Sydney’s busiest arterial roads and surrounded by a built-up retail, commercial and residential precinct;
  • Limited space for the delivery of materials, crane installation and removal;
  • Heavy lifting requirements – precast and steel elements weighing up to 120T; and
  • Construction schedule – driven by where the project sat within Sydney Metro’s overall project delivery schedule for the Sydney Metro City & Southwest line.
OUR SOLUTION

Working closely with Sydney Metro’s design and engineering team for 18 months during the front-end design phase allowed Sydney Metro to adopt their preferred design for manufacture and assembly (DfMA) construction methodology.

Taking buildability, time, and safety into consideration, Marr’s solution aligned the cranage with the construction methodology to help secure the construction program.

Using two of Marr’s M2480Ds installed within the station box, the bespoke cranage solution addressed the challenge of how to provide the heavy lifting capacity the project needed within the small space of the station box construction site. Our approach also addressed the other logistical challenges that came with the lack of space available for the delivery of materials to site and the handling of large precast and steel elements weighing up to 120 tonnes.

THE RESULT

Marr’s expertise resulted in a cranage solution that:

  • Supported Sydney Metro’s preferred DfMA construction approach – allowing larger and heavier structures to be fabricated off-site and installed in single lifts;
  • Aligned the cranage solution with the construction program ­– supporting the delivery of the project to the overall construction schedule of the Sydney Metro City & Southwest project;
  • Eliminated the need for temporary works;
  • Provided a solution that was safer, more efficient, and cost-effective; and
  • Allowed Sydney Metro to issue a considered and evaluated design for the construction tenderers with a suitable cranage solution built into it – enabling the project could transfer easily from contract award to construction in a short timeframe.

Our early engagement on this project supported Sydney Metro’s desire to adopt a designed for manufacture and assembly (DfMA) construction approach. Then it was about aligning the cranage to that approach and using it to help secure the programme with a safer, more efficient and cost-effective solution.”

– Simon Marr, Managing Director, Marr Contracting

LET'S TALK ABOUT HOW WE COULD ADD VALUE TO YOUR PROJECT

We work with our clients to find a craneage solution that works – no matter how big or complex the job is. If the right crane doesn’t already exist, we’ll build one to suit the needs of your project.

ABOUT US

We’re not just a crew and cranes for hire. We’re big thinkers and problem solvers who love a challenge. No problem is too big for us.

OUR PHILOSOPHY

We believe that the crane needs to suit the job, not the other way around. We don’t just hire cranes – we design craneage solutions.

OUR HERITAGE

We’re a third-generation family-owned and run business with a strong sense of tradition and loyalty engrained in what we do and how we work together.

OUR PEOPLE

We think of our team as ‘one big family’ of problem-solvers who love cranes and the challenge of working on complex, large-scale projects.

OUR APPROACH

We work with you to find an engineering solution that works. Delivering value through the unique combination of our knowledge, experience, proven service delivery and people.

OUR SERVICES

We’ve worked on some of the most complex and challenging large-scale construction projects across Australia and around the world.

OUR CRANES

We don’t just hire cranes – we design them. So, if the right crane for your job doesn’t already exist, we’ll build one.

OUR PROJECTS

With almost 100 years’ experience, we have a reputation for taking on projects that others can’t or won’t.

SAFETY, QUALITY & ENVIRONMENT

We take on the jobs that many others can’t or won’t – but we always put good business practices first.

SUSTAINABILITY

We take sustainability seriously. It’s inherent in our commitment to finding the best and most efficient solution to every job.

SOCIAL IMPACT

As problem-solvers who love a challenge, we are never shy of tackling the big issues.

DIVERSITY

We are committed to creating a diverse, inclusive and flexible workplace that reflects the clients and communities we work with.