WASTE TO ENERGY PROJECT

WASTE TO ENERGY PROJECT

A cranage solution to withstand the ‘Fremantle Doctor’

SHARE

PROJECT OVERVIEW

Located 40 kilometres south of Perth, this AU$511 million Waste to Energy Project is the second large-scale waste to energy (WtE) plant to be built in Australia.

After our client was awarded the lead contract for engineering, procurement and construction (EPC) on the project in 2019, they contacted Marr Contracting to work with them to develop a heavy lifting strategy and cranage solution to support their planned modular construction methodology.

Client
UNDISCLOSED
Project
WASTE TO ENERGY PROJECT
Location
WESTERN AUSTRALIA
Sector
POWER GENERATION
Date
2021-2022
Cranes

1 x M2480D

THE CHALLENGE

Located in a high wind area close to the coast, the climatic conditions of the greenfield site posed a number of challenges that our client wished to address based on their experiences constructing similar projects. Their primary concern was to find a solution that would decrease the number of lifting activities on the project and reduce the risks that wind played in this region of Western Australia where the ‘Freemantle Doctor’ afternoon sea breeze often blows at a rate of 20 knots (37km) per hour.

“We contacted Marr at the initial planning stage because they had a solution that would minimise interface and project risk with a ‘one size fits all’ crane,” said the project’s Construction Manager.

OUR SOLUTION

Working closely with our client’s construction team during the early stages of the project, we were able to design a simple craneage solution that reduced the number of cranes required. This reduced congestion onsite and allowed for pre-assemblies at ground level, which reduced the number of activities at height and improved onsite safety.

We also completed an analysis of historical wind data which indicated that the project was at risk of having its crane lifting operations impacted by wind on 75 per cent of days across a 12-month period if a traditional crawler or mobile crane methodology was adopted. This figure increased to over 90 per cent of days being wind-affected during the summer months – highlighting that a different approach to lifting was required if the project’s craneage solution was to be successful.

Marr’s solution – using a 330-tonne capacity M2480D Heavy Lift Luffer (HLL) stood on one of our ballasted static bases and crane mat system – allowed critical lifts, weighing up to 150 tonnes, to be completed by a single crane from a fixed location. With a total site coverage of over 32,000 square meters and an ability to place 25 tonnes anywhere within the crane’s 102-meter radius, we were able to open up areas of the site for pre-assemblies and lay-down. This helped to significantly reduce congestion across the site.

The ability of the M2480D to work unaffected in wind speeds up to 20 meters a second, (which is double that of a traditional crawler or mobile crane approach), meant that we could de-risk the planned lifting operations from the delays that we had identified early in the crane planning process.

THE RESULT

Marr’s M2480D crane solution delivered a simple, ‘clean’ crane solution to the project team that:

  • increased availability by eliminating risk associated with delays caused by wind – our solution meant that less than 1% of days were affected;
  • reduced onsite work by lifting larger and heavier pre-assembled modules including structural steel cubes and boiler pressure parts (up to 98T) and a steam boiler drum, which reduced:
    • working-at-height risk
    • onsite welding, heat treatment and Non-Destructive Testing (NDT)
  • reduced the number of cranes on the project, which:
    • provided a de-congested and safer site
      removed the complexity associated with multiple crane operations in numerous areas
    • simplified lift planning
    • switched the focus to delivering construction instead of crane co-ordination
  • required little ground improvement or expensive civil construction works; and
  • allowed the site to react to unscheduled lifting requirements.
LET'S TALK ABOUT HOW WE COULD ADD VALUE TO YOUR PROJECT

We work with our clients to find a craneage solution that works – no matter how big or complex the job is. If the right crane doesn’t already exist, we’ll build one to suit the needs of your project.

“This is a great example of a client engaging us early in the construction planning stage of the project to achieve a safer, more-efficient lifting solution, that importantly drives program security for the project,” said Marr’s Managing Director, Simon Marr.

LET'S TALK ABOUT HOW WE COULD ADD VALUE TO YOUR PROJECT

We work with our clients to find a craneage solution that works – no matter how big or complex the job is. If the right crane doesn’t already exist, we’ll build one to suit the needs of your project.

ABOUT US

We’re not just a crew and cranes for hire. We’re big thinkers and problem solvers who love a challenge. No problem is too big for us.

OUR PHILOSOPHY

We believe that the crane needs to suit the job, not the other way around. We don’t just hire cranes – we design craneage solutions.

OUR HERITAGE

We’re a third-generation family-owned and run business with a strong sense of tradition and loyalty engrained in what we do and how we work together.

OUR PEOPLE

We think of our team as ‘one big family’ of problem-solvers who love cranes and the challenge of working on complex, large-scale projects.

OUR APPROACH

We work with you to find an engineering solution that works. Delivering value through the unique combination of our knowledge, experience, proven service delivery and people.

OUR SERVICES

We’ve worked on some of the most complex and challenging large-scale construction projects across Australia and around the world.

OUR CRANES

We don’t just hire cranes – we design them. So, if the right crane for your job doesn’t already exist, we’ll build one.

OUR PROJECTS

With almost 100 years’ experience, we have a reputation for taking on projects that others can’t or won’t.

SAFETY, QUALITY & ENVIRONMENT

We take on the jobs that many others can’t or won’t – but we always put good business practices first.

SUSTAINABILITY

We take sustainability seriously. It’s inherent in our commitment to finding the best and most efficient solution to every job.

SOCIAL IMPACT

As problem-solvers who love a challenge, we are never shy of tackling the big issues.

DIVERSITY

We are committed to creating a diverse, inclusive and flexible workplace that reflects the clients and communities we work with.